A rockslide off the coast of Côte d'Ivoire, an anchor dragged by a stricken cargo ship in the Red Sea, and a still-unexplained cut near Jeddah eighteen months later: three unrelated incidents, two oceans apart, produced the same outcome. Large parts of Africa and Asia lost fast, reliable internet access for days or weeks. The pattern is now familiar enough to draw a hard conclusion: the world's digital backbone runs through a small number of physical chokepoints, and neither Africa's west coast nor the Red Sea corridor has enough redundancy to absorb a single failure gracefully.
Three incidents, one lesson
On March 14, 2024, a suspected underwater rockslide near Abidjan damaged four separate submarine cables at once — ACE, SAT-3/WASC, WACS and MainOne — because their routes converge at that single point off Côte d'Ivoire [1]. The outage reached 13 countries along the West African seaboard, from Benin and Ghana to Nigeria and South Africa, and full restoration took until mid-May, with different cables coming back online in stages over roughly two months [1]. Banks, mobile-money platforms and call centers that depended on a single upstream provider were the hardest hit, because they had no second physical path to fail over to.
A year earlier, in February 2024, the UK-registered vessel Rubymar was struck during a Houthi attack in the Red Sea and drifted with its anchor deployed, severing the AAE-1, EIG and SEACOM cables that connect Asia, the Middle East, Africa and Europe [2]. Then, on September 6, 2025, the SMW4 and IMEWE systems were cut near Jeddah, Saudi Arabia, pushing Microsoft Azure and other cloud traffic onto longer alternate routes and raising latency for real-time applications across Asia and the Middle East [2]. Independent monitors reported degraded connectivity as far as Pakistan and India [3].
Why the same corridors keep failing
Two geographic facts explain the repetition. First, roughly 17% of global internet traffic transits Red Sea cables, and about 80% of Asia-to-West traffic uses that corridor, so any damage there has an outsized effect relative to the physical size of the waterway [2]. Second, on Africa's Atlantic coast, several of the continent's main cables were engineered to land at the same few points, which is efficient to build but means a single seabed event can sever multiple systems simultaneously — exactly what happened off Côte d'Ivoire [1].
This is a structural problem, not a series of unlucky accidents. Submarine cable routes are chosen for the shortest, cheapest path between markets, and multiple operators independently converge on the same geography for the same commercial reasons. The result is a network that looks redundant on a map — many cable names, many operators — but is not redundant in practice, because the cables share physical corridors.
What actually cushions the blow
Countries and companies that recovered fastest from these outages had three things in common:
- Multiple, geographically distinct upstream routes rather than reliance on a single submarine system
- Local internet exchange points (IXPs) that keep domestic traffic — banking, government services, local content — off international cables entirely
- A working alternative, such as satellite backhaul, that can absorb critical traffic during repairs
The Internet Society's review of the 2024 West Africa outage points to exactly this mix: more cables with diverse landing points, expanded IXPs, locally cached content, and newer options such as low-earth-orbit satellite service and the 2Africa cable system as practical mitigations rather than theoretical ones [1]. None of these fixes is new or exotic; the constraint has been investment and coordination, not technical knowledge.
The repair timeline problem
Even when the diagnosis is simple, the fix is slow. Specialized cable-repair ships are scarce globally, and a vessel may need days just to reach a fault site before repair work — which can take a week or more per cable — even begins. In the West Africa case, the four affected cables did not return to full service on the same day; restoration was staggered from late March into mid-May 2024, because each cable required its own vessel time and each fix had to be sequenced [1]. For a business, a government agency or a bank branch depending on one upstream link, "the cable is being repaired" can mean a month, not a day, of degraded service.
What this means for planning, not just infrastructure
For any organization operating in a market that depends on one or two submarine cables, the practical response is the same whether the outage originates near Jeddah or Abidjan: treat single-path internet connectivity as a known, recurring risk rather than a rare event, and budget for a genuinely separate backup path — a different cable system, a different border crossing, or a satellite link — rather than a second contract with the same underlying route. Cable cuts of this kind are not becoming less frequent; they are simply becoming better documented. Planning around that reality, rather than around the assumption that undersea cables rarely fail, is the more defensible baseline going forward.